Changing your EMS provider may seem like a straightforward process, but in practice it requires careful preparation. One of the biggest risks is not the production process itself, but the loss of project knowledge: engineering change history, process settings, test results, or detailed information about the components used.
That is why a well-managed transfer starts long before the project reaches the production line.
The first stage is to verify the completeness of the technical documentation. We review, among other things, the BOM, assembly documentation, test specifications, and engineering change history.
This stage may reveal outdated part numbers, EOL components, inconsistencies in the documentation, or missing information required to prepare the production process correctly.
If an alternative component is needed, its selection and qualification are carried out in consultation with the customer.
A production transfer often also involves components and materials remaining at the previous EMS provider. Depending on the project, we analyze the possibility of taking over or purchasing these stocks in order to reduce the risk of duplicate costs and help ensure production continuity.
At this stage, component availability and potential sourcing risks are also reviewed.
Once the documentation has been organized, we move on to preparing the production process.
Elhurt EMS operates three SMT lines, two of which have been comprehensively modernized. In our quality control processes, we use technologies including SPI and AOI, as well as Flying Probe for selected projects, particularly in low-volume production where preparing a dedicated ICT fixture would not be economically justified.
Depending on the project requirements, dedicated test solutions may also be prepared or further developed.
The first batch after the transfer is used to validate the entire process under conditions as close as possible to serial production.
We verify, among other things, compliance with the documentation, test results, assembly quality, and any process deviations. Only after reviewing the results do we decide whether the project is ready to move into stable serial production or whether the process still requires adjustments.
Skipping this stage increases the risk that problems will only become visible at higher production volumes.
Throughout the transfer process, the customer has clearly assigned contacts responsible for the project, supported by a dedicated team covering the individual implementation stages.
This helps prevent project knowledge from becoming fragmented and allows decisions regarding documentation, components, testing, and production to be made efficiently and with full technical context.
As Sławomir Tkacz, Managing Director of Elhurt EMS, explains:
“We do not tell the customer: here is a catalogue of our capabilities, see if there is something that suits you. As an EMS company, we need to understand exactly what the customer expects.”
In a production transfer, this approach has very practical value: the better we understand the project at the beginning, the lower the risk of problems at later stages.
A production transfer does not eliminate all project risk and does not replace the customer’s R&D team if the product requires design changes.
Elhurt EMS focuses on preparing the project for production, implementation, process optimization, assembly, testing, and integration. Designing electronics from scratch is not the core scope of our EMS activity and may be delivered through design capabilities available within the Group.
Our goal is not to promise a “problem-free transfer”, but to reduce risk through a structured process, validation, and clear responsibility at every stage.
If you are considering changing your EMS provider, it is best to start the discussion before cooperation with your current supplier comes to an end. The earlier the documentation, BOM, engineering change history, and available inventory can be reviewed, the easier it is to plan the transfer without unnecessary production downtime.
Discuss your production transfer with the Elhurt EMS team.
We use cookies to help users navigate efficiently and perform certain functions. Detailed information about all cookies corresponding to each consent category is provided below.
Cookies classified as “necessary” are stored in the user’s browser because they are essential for enabling the basic functions of the website.
We also use third-party cookies that help us analyze how users interact with the website, store user preferences, and provide relevant content and advertisements. These types of cookies will only be stored in the browser with the user’s prior consent.
You can enable or disable some or all of these cookies, but disabling some of them may affect your browsing experience.
| Cookie | Duration | Description |
|---|---|---|
| _GRECAPTCHA | 180 days | |
| __cf_bm | 0 minutes | Cloudflare Bot Management — distinguishes humans from bots. |
| rc::* | Persistent | Google reCAPTCHA — localStorage used to store the state of the anti-bot challenge. |
| Cookie | Duration | Description |
|---|---|---|
| wp-wpml_current_language | Session | WPML — stores the current language. |
| Cookie | Duration | Description |
|---|---|---|
| _ga | 400 days | Google Analytics — distinguishes unique users based on a client identifier. |
| _ga_* | 400 days | Google Analytics 4 — maintains the session state for individual properties. |
| Cookie | Duration | Description |
|---|---|---|
| _gcl_au | 90 days | Google AdSense/Ads — experiments related to ad effectiveness (conversion tracking tool). |
| test_cookie | 0 minutes | Google DoubleClick — checks whether the browser supports cookies. |
| Cookie | Duration | Description |
|---|---|---|
| _lscache_vary | 2 days | |
| _lfa | 365 days | |
| bcookie | 365 days | |
| li_gc | 180 days | |
| lidc | 1 day |